We have had a very successful first week at our site in Fleet... Even though Storm Gareth gave us a battering! 🌧🌧🌧 We have demolished the existing two-storey extension, started internal remodelling and demolition, excavated the trenches ready for the foundations, and today we poured the foundations... which involved 15 cubic meters of concrete! 👌🏼 Now we are going to have a well deserved rest this weekend so we are ready to start the foundation block work and install a new drainage system next week...







 
 
 